Road Closure: Stanton St., 146th Ave. to 120th Ave., Olive Twp., begins June 3, 2024

Project consists of culvert replacement, road resurfacing

WHAT: Road Closure

WHEN: June 3-July 4, 2024

WHERE: Stanton St., 146th Ave. to 120th Ave., Olive Twp.

WHY: Culvert Repair/Resurfacing

BACKGROUND: The Ottawa County Road Commission will close Stanton Street between 146th Ave. and 120th Ave. in Olive Township beginning Monday, June 3, 2024, for a culvert replacement project and upcoming resurfacing work.

The culvert replacement is located immediately to the west of the 120th Ave./Stanton St. intersection. As a result of this work, local traffic will not be able to access Stanton St. from 120th Ave. during the culvert replacement portion of the project. All local traffic will be required to access the area from west.

The culvert replacement work is expected to last until June 21.

The closure will remain in place following the culvert replacement for a resurfacing project on Stanton Street between U.S. 31 and 120th Ave.

Work on Stanton St. between U.S. 31 and 142nd Ave. will consist of milling down existing asphalt, adding a paved shoulder, resurfacing the road with new asphalt, and gravel shoulder restoration.

Work on Stanton St. between 142nd Ave. and 120th Ave. will consist of crushing and shaping existing asphalt to gravel, grading material for new a new road width of 30 feet, resurfacing the road with new asphalt, and gravel shoulder restoration.

The resurfacing portion of the work is expected to last through July 4, 2024.

Note: All dates are tentative, and all work is weather dependent.

DETOUR: The road will be closed to thru traffic. A signed detour for Stanton St. will utilize 146th Ave./Fillmore St./120th Ave.

To view a map of all current road closures and resurfacing projects, visit our online OCRC Road Closures dashboard.