Road Resurfacing: Kelly St., Fruitport Rd. to 148th Ave., Spring Lake Twp., begins July 25, 2024

START DATE: July 25, 2024

ESTIMATED FINISH: Early August

WHERE: Kelly St., Fruitport Rd. to 148th Ave., Spring Lake Twp.

WHY: Road Resurfacing

BACKGROUND: Beginning the Thursday, July 25, 2024, contractors for the Ottawa County Road Commission will begin a resurfacing project on Kelly St. from Fruitport Rd. to 148th Ave. in Spring Lake Twp.
This project will consist of milling existing asphalt, adding a paved shoulder for a new road width of 24 feet, resurfacing with 2 lifts of new asphalt, and gravel shoulder restoration.
This project is expected to last through early August 2024, however all work is weather dependent and completion dates are subject to change.

TRAFFIC IMPACT: The road will remain open to through traffic; however traffic will be maintained using temporary lane closures under flag control during work hours. Be prepared for possible delays when traveling through this area during project hours.


Kelly St. Road Resurfacing – July 2024

To view a map of all current road closures and resurfacing projects, visit our online OCRC Road Closures dashboard.