Weekly Construction Update: June 14, 2024: OCRC Construction Update

For regular updates, visit our current road work and closures website and view an interactive road work map. You can also visit our website to view a list of all planned OCRC construction projects for the current construction season. Be sure to follow our Facebook, Instagram and X accounts for up-to-date Road Commission information.

Note: The OCRC does not list construction projects for Michigan Department of Transportation work or local cities/villages in Ottawa County. For information about these projects, visit the MDOT construction project map or find your local municipality’s website.


Road Closure Update: New Holland St., U.S. 31 to 136th Ave., Olive Twp.
DURATION: June 17-24, 2024
WHERE: New Holland St.: U.S. 31 to 136th Ave., Olive Twp.
WHY: Culvert Failure Repair
BACKGROUND: Contractors for the Ottawa County Road Commission will be making repairs to the failed culvert on New Holland St. between U.S. 31 and 136th Ave. in Olive Township the week of June 17, 2024.
The project is expected to last for one week, and the road will reopen once the repairs are completed.
The road has been closed since March following an on-site inspection by OCRC engineers who determined that there was a failed culvert. The OCRC was required to obtain and was waiting on necessary permits before work could take place on the repair.
TRAFFIC IMPACT: The current detour in place consisting of U.S. 31/Van Buren St./136th Ave. remains in place for the duration of the closure.


Road Resurfacing: Gooding St., 48th Ave. to 32nd Ave., Chester Twp., begins June 17, 2024
START DATE: Week of June 17, 2024
ESTIMATED FINISH: June 28, 2024
WHERE: Gooding St., 48th Ave. to 32nd Ave., Chester Twp.
WHY: Road Resurfacing
BACKGROUND: Beginning the week of June 17, 2024, contractors for the Ottawa County Road Commission will begin a resurfacing project on Gooding St. from 48th Ave. to 32nd Ave. in Chester Twp.
This project will consist of milling down existing asphalt, adding a 3-foot paved shoulder, resurfacing the road with 2 layers of new asphalt, and gravel shoulder restoration.
This project is expected to last through late June 28, 2024, however all work is weather dependent and completion dates are subject to change.
TRAFFIC IMPACT: The road will remain open to through traffic; however traffic will be maintained using temporary lane closures under flag control during work hours. Be prepared for possible delays when traveling through this area during project hours.


Road Resurfacing: Van Buren St., 48th Ave. to 40th Ave., Georgetown Twp., June 20-July 17, 2024
START DATE: June 20, 2024
ESTIMATED FINISH: July 17, 2024
WHERE: Van Buren St., 48th Ave. to 40th Ave., Georgetown Twp.
WHY: Road Resurfacing
BACKGROUND: Beginning the week of June 20, 2024, contractors for the Ottawa County Road Commission will begin a resurfacing project on Van Buren St. from 48th Ave. to 40th Ave. in Georgetown Twp.
This project will consist of milling off the existing asphalt surface, adding paved shoulders up to 3 feet in width on each side of Van Buren St. where conditions allow, and paving 2 layers of new asphalt.
This project is expected to last through July 17, 2024, however all work is weather dependent and completion dates are subject to change.
TRAFFIC IMPACT: The road will remain open to through traffic; however traffic will be maintained using temporary lane closures under flag control during work hours. Be prepared for possible delays when traveling through this area during project hours.


Road Closure: W. Spring Lake Rd., Taft St. to Hemlock Dr., June 17-29, 2024
WHAT: Permitted Road Closure
WHEN: June 17-29, 2024
WHERE: W. Spring Lake Rd.: Taft St. to Hemlock Dr. (W. Fruitport Rd.), Spring Lake Twp.
WHY: Sanitary Sewer Crossing
BACKGROUND: A private contractor has a permit to close W. Spring Lake Rd. between Taft St. and Hemlock Dr. (W. Fruitport Rd.) in Spring Lake Twp. in order to install sanitary sewer crossings in 2 spots.
Spring Lake Rd. will be closed from for 2 weeks starting June 17, 2024, through June 29, 2024.
TRAFFIC IMPACT: Taft St. to 168th Ave. to Hemlock Dr. (W. Fruitport Rd.)
Current Projects & Closures

TOWNSHIPROADSEGMENTWORKDATESTRAFFIC
GeorgetownVan Buren St.48th Ave. to 40th Ave.ResurfacingJune 20-July 17Lane Closures
OliveStanton St.U.S. 31 to 120th Ave.ResurfacingJune 19-July 4Road Closed
Wright14th Ave.Roosevelt St. to Hickory St.Culvert ReplacementJune 17-18Road Closed
Spring LakeW. Spring Lake Rd.Taft St.to Hemlock Dr.Sanitary CrossingJune 17-29Road Closed
ChesterGooding St.48th Ave. to 32nd Ave.ResurfacingJune 17-30Lane Closures
Chester32nd Ave.Wilson St. to Sehler St.ResurfacingJune 11-30Lane Closures
Chester32nd Ave.Harrisburg Rd. to Truman St.ResurfacingJune 11-30Lane Closures
Grand HavenFerris St.152nd Ave. to 168th Ave.Force MainJune 10-July 30Road Closed
Allendale64th Ave.Fillmore St. to M-45ResurfacingJune 10-28Lane Closures
Olive146th Ave. to 120th Ave.Culvert ReplacementJune 3-July 4Road ClosedAllendale
Allendale56th Ave.M-45 to Rich St.Sanitary SewerMay 28-July 12Road Closed
Holland106th Ave.At BL-196ReconstructionMay 28-Aug. 1Road Closed
Park1st Ave.South Shore Dr. to 32nd St.Sanitary Sewer/DrivewayMay 14-June 14Road Closed
RobinsonSleeper St.120th Ave. to 104th Ave.ReconstructionApril 8-July 19Road Closed
RobinsonGreen St.144th Ave. to 128th Ave.Bridge/Path WorkApril 1-Sept. 6Detour Map
OliveNew Holland St.U.S. 31 to 136th Ave.Culvert FailureMarch 29-June 24Road Closed
Allendale40th Ave.M-45 to Bliss St.Road ReconstructionMarch 19-June 30Detour Map
Polkton/Wright48th Ave.Roosevelt St. to Taft St.CulvertDec. 1-TBARoad Closed

Subdivision Resurfacing Program

TOWNSHIPTIMELINE
GeorgetownApril 29-July 31

All dates listed in the above tables are estimates and are subject to change without notice. Always obey all work zone and road closure signs and be sure to follow all posted detours.

Work With Us: You Play a Role in Work Zone Safety!
Lane closures, traffic pattern shifts and reduced speeds are common in work zones. Make sure to slow down when entering a work zone and keep an eye out for road workers.